Emergency with Resiliency Equals Efficiency - Challenges of an EMT-3 in Nepal.

Prehospital and Disaster Medicine · 2018-11-15 · Observational study

Abstract

The 7.8 MW (moment magnitude scale) earthquake that hit Nepal on April 25, 2015 caused significant casualties and serious damage to infrastructure.The Israeli Emergency Medical Team (IEMT; later verified as EMT-3) was deployed 80 hours after the earthquake. A Forward Disaster Scout Team (FDST) that was dispatched to the disaster area a few hours after the disaster relayed pre-deployment information.The EMT staff was comprised of 42 physicians. A total of 1,668 patients were treated. The number of non-trauma cases increased as the days went by. The hospitalization rate was 31%. Wound debridement procedures were the most common operations performed. YitzhakA, MerinO, HalevyJ, TarifB. Emergency with resiliency equals efficiency- challenges of an EMT-3 in Nepal. Prehosp Disaster Med. 2018;33(6):673-677.

Tags

Low- and middle-income settings · Prehospital physicians